A Detroit-Area Bottling Plant's Can-Line Floor — Rebuilt in 59 Hours

In 2025, Maverick Performance Solutions rebuilt 8,600 square feet of production flooring for a Michigan beverage bottler inside a hard 72-hour shutdown — and handed the floor back in 59 hours. Instead of relocating drains, Maverick built the slope to them: a sloped urethane cement overlay up to 6 inches thick, formed with custom curb forms and pitched to the plant's existing drains, alongside 7,200 SF of MavCoat PC epoxy.

The Job at a Glance

Client A Michigan beverage bottler (name withheld)
Location Metro Detroit, Michigan
Industry Beverage bottling — an FDA-regulated operation
Square footage 8,600 SF total, installed 2025
System — Zone 1 (7,200 SF) MavCoat PC broadcast epoxy
System — Zone 2 (can-line footprint) Urethane primer → MavGrout USP integral curbs + sloped overlay, up to 6″ thick to drain → MavCrete UM skim coat → 2 coats MavSeal UPA
Substrate condition found Major cracking and spalls in the can-line footprint; existing drains in the wrong locations for the new line
Surface prep Shot blast + scarify; elevation mapping to set the slopes
Shutdown window 72 hours, hard deadline
Return to service 59 hours — 13 hours inside the deadline
Warranty 2-year single-source warranty covering materials and labor — Maverick engineered, manufactured, and installed the system

A New Can Line, an Old Floor, and Drains in the Wrong Place

The plant was installing a new can line — and the floor in its footprint was not going to pass. The existing concrete did not meet the sanitary flooring requirements of an FDA-regulated bottling operation: major cracking and spalls ran through the exact area where the new line would sit, and the existing drains were in the wrong locations for the new equipment layout.

Cracked, porous concrete under a beverage line is more than a wear problem. Washdown water finds every crack, and a floor that can't be cleaned to the standard the facility's regulatory environment demands puts the line itself at risk. The floor had to be rebuilt — correctly, and sanitary by design — before the new can line could go in. This is the problem set our food & beverage flooring work exists to solve.

Cracked and worn concrete slab in a bottling plant can-line footprint before repair
Before: cracked, worn concrete in the can-line footprint.

72 Hours. Everyone Else Said No.

The plant could give the project exactly one window: a hard 72-hour shutdown. Every hour past it was lost production. Other contractors looked at the schedule and declined — and their recommended fix, relocating the drains to match the new line, meant demolition, underslab plumbing, added cost, and weeks of downtime the bottler didn't have. The job as everyone else scoped it could not be built in the window that existed. So Maverick scoped a different job.

Don't Move the Drains. Build the Slope to Them.

Maverick's in-house engineering flipped the problem. The drains weren't wrong — the floor was flat. Instead of relocating the drains to suit the new can line, we kept every drain where it was and rebuilt the floor above them: a full sloped overlay within the can-line footprint, pitched so that washdown water runs to the existing drains from the new line's layout.

The build: custom rapid-strip curb forms — designed and fabricated by Maverick — defining an integral containment curb around the pad, with up to 6-inch-thick sloped urethane grout placed to drain in a single day. MavGrout USP formed the curbs and the sloping overlay, a MavCrete UM skim coat tightened the surface, and two coats of MavSeal UPA finished the system. Because Maverick manufactures the MavCrete urethane cement systems it installs, the slope geometry, the material, and the crew plan were engineered together — one company, one 72-hour answer. Around the pad, the remaining 7,200 SF got a MavCoat PC broadcast epoxy floor, so the whole 8,600 SF area came back as one seamless, cleanable system.

3D model render of integral containment curb design options for a sloped bottling plant floor
Maverick's 3D curb model options, from the design phase.

59 Hours, in Order

  • 1. Prep. Shot blast and scarify across the full 8,600 SF — the cracked, spalled surface mechanically removed down to sound, profiled concrete.
  • 2. Elevation mapping. The crew shot elevations across the can-line footprint and mapped every slope to its drain before a single form was set. On a floor this thick, the geometry is the spec.
  • 3. Forms. Maverick's custom rapid-strip curb forms went in on the mapped lines — fabricated for this pour, designed to strip fast enough to keep the schedule moving.
  • 4. The pour. Up to 6 inches of sloped MavGrout USP urethane grout, curbs and overlay, placed to drain in a single day.
  • 5. Finish. MavCrete UM skim coat over the overlay, then two coats of MavSeal UPA. Zone 1's 7,200 SF of MavCoat PC epoxy went down alongside.
  • 6. Handback. The plant was back in production at hour 59 — 13 hours before the deadline.

The 25-Foot Squeegee

One stretch of the pour ran under equipment nobody could reach: 18 feet of no-access condensers spanning a 140-foot run. There is no standard tool that places and finishes flooring material under a machine you cannot stand beside — so Maverick built one. Maverick designed and fabricated a custom 60-inch squeegee with a 90-degree pivot head on a 25-foot extension pole, letting an installer work material to grade deep under the condensers from open floor.

The assessment walk — surveying the no-access condenser run before the pour.

“I'm trying to see if we can access 18 feet… extension poles to seal it under there — we've got maybe six inches of clearance.”

— Maverick's founder, on the assessment walk that produced the 25-foot squeegee
Welded 90-degree pivot bracket for the custom squeegee, on the fabrication bench
The welded pivot bracket, mid-fabrication
Welding the custom squeegee assembly after hours
Fabrication didn’t wait for business hours
Completed 60-inch squeegee blade assembly on the fabrication bench
The completed blade assembly
Finished custom 60-inch pivoting squeegee tool
The finished 60-inch pivot squeegee

It worked flawlessly. The floor under the condensers carries the same slope, the same finish, and the same system as the floor in the open — and the condensers never moved. This is what it means to have the manufacturer's engineering on the install crew: when the job needs a tool that doesn't exist, we fabricate it, the same way we fabricated the curb forms.

Back in Production in 59 Hours

The bottler got its floor back 13 hours before the 72-hour deadline — a deadline other contractors wouldn't touch. The integral curb contains washdown water within the can-line pad, and the rebuilt floor carries a true 1/4-inch-per-foot slope to the existing drains — zero ponding under full washdown.

The drains never moved. The weeks of downtime and underslab plumbing in every other proposal never happened. And the new can line went in on a seamless, sloped, cleanable floor built for the sanitary flooring requirements of an FDA-regulated bottling operation — engineered, manufactured, and installed by one company based 20 minutes from most Metro Detroit plants.

Finished sloped urethane cement pad with integral containment curb at a bottling plant
Finished: sloped pad with integral containment curb.
Crew mapping floor elevations and the curb line inside a bottling plant

Mapping elevations and the curb line

Custom rapid-strip curb forms set on the prepared slab

Custom rapid-strip curb forms, fabricated for this pour

Perforated aluminum rapid-strip curb form set to the layout line

Curb form detail — set to the layout line

Installation crew placing the urethane containment curb inside the forms

Placing the containment curb inside the forms

Sloped urethane cement overlay being screeded to grade

The sloped overlay taking shape

Crew screeding the sloped urethane overlay to grade against the curb form

Screeding the sloped overlay to grade at the curb line

Cracked, worn concrete in the can-line footprint before the rebuild

Before: cracked, worn concrete in the can-line footprint

Finished floor in the condenser area, coated beneath equipment with the custom 25-foot squeegee

After: the condenser area — coated beneath equipment with the custom 25-ft squeegee

Facing thermal shock, washdown, or a slope-to-drain rebuild of your own? Start with our urethane cement flooring service — the same system family that carried this floor.

Have a Floor Like This One?

Tell us the square footage, the exposure, and the shutdown window — especially the shutdown window. An engineered build-up recommendation and budget direction come back within 48 hours. That's our promise.